# ITRCC Announces Mile Marker 10 to Mile Marker 20 Anticipated Construction Schedule

- Link: https://europeanbusinessmagazine.com/itrcc-announces-mile-marker-10-to-mile-marker-20-anticipated-construction-schedule/
- Published: 2024-08-07T16:00:00+00:00
- Author: EBM Mediawire

_**Pavement improvements to begin in Lake County, IN.**_

**ELKHART, IN / ACCESSWIRE / August 7, 2024 / **ITR Concession Co. LLC (ITRCC), 
the concessionaire and operator of the Indiana Toll Road, is announcing that construction
work from mile marker 10 (Exit 10 Gary/Chicago International Airport) to mile marker
20 (just west of the Indiana Toll Road Lake Station Exit 21 Toll Plaza) will commence
September 9, 2024, weather permitting.

The work will consist of eastbound (EB) and westbound (WB) mainline milling and 
paving operations, which will include intermittent and short-term lane and shoulder
closures. This comprehensive project will also include the resurfacing of the Gary
West Exit 14A interchange, which will necessitate its temporary closure. ITRCC will
also take the opportunity to resurface ramps during the INDOT Broadway 14B closure.
To expedite the overall project schedule, the majority of the construction will 
occur Monday through Saturday during daytime operations.

### Join The European Business Briefing

New subscribers this quarter are entered into a draw to win a Rolex Submariner. 
Join 40,000+ founders, investors and executives who read EBM every day.

 [Subscribe](https://europeanbusinessmagazine.beehiiv.com/subscribe)

Additionally, nighttime work will take place at the Gary East Exit 17 and Lake Station
Exit 21 toll plazas anticipated to begin in August requiring intermittent toll lane
closures; the plazas will remain operational during this time. In observance of 
the Labor Day holiday, all construction activities will be temporarily halted.

**Anticipated Project Timeframe September – November Phasing**

 * There will be one travel lane of traffic during each respective phase:
    - WB MM 10-15.6 (9/9/24 – 10/1/24)
    - EB MM 10-15.6 (9/26/24 – 10/23/24)
    - EB/WB MM 16.5-20 (10/18/24 – 11/21/24)
 * Gary West Exit 14A closure
    - WB week of 9/21
    - EB week of 10/15

*Dates subject to change due to materials, equipment, or weather delays.

For more information on traffic impacts and project updates, please visit [IndianaTollRoad.org](https://stats.nwe.io/x/html?final=aHR0cHM6Ly9JbmRpYW5hVG9sbFJvYWQub3Jn&sig=F2XBLOvhLByqe6rQLYHxhASlzdk-5gQMOUJTrQ0lQZQ1gLo0GmnQjqrZ7oaNmDOqBWM0mn6cNpD7_CP2FqwvNg&hit%2Csum=WyI0Z2dkYWwiLCI0Z2dkYW0iLCI0Z2dkYW4iXQ).

**About the Indiana Toll Road**

Established in 2006, the ITR Concession Company LLC (ITRCC) responsibilities are
detailed in the Concession and Lease Agreement with the Indiana Finance Authority,
such as the construction, maintenance, repair, and operation of the 157-mile Indiana
Toll Road. Headquartered in Elkhart, the Toll Road spans northern Indiana, linking
Chicago with the Eastern Seaboard. Designated as part of Interstate 80/90, the Toll
Road serves as a vital transportation link in the Midwest.

**Contact Information**

Yvette Leyva 
_Communications Specialist_ [yleyva@indianatollroad.org](https://europeanbusinessmagazine.com/itrcc-announces-mile-marker-10-to-mile-marker-20-anticipated-construction-schedule/yleyva@indianatollroad.org)
5742614028

**SOURCE:** ITR Concession Company LLC

![.](https://stats.nwe.io/x/im?ref=WyI0Z2dkYW8iXQ&hit,sum=WyIyazVia2kiLCIyazVia2oiLCI0Z2dkYW8iLCI0Z2dkYXAiXQ)

View the original [press release](https://www.newswire.com/news/itrcc-announces-mile-marker-10-to-mile-marker-20-anticipated-22402785)
on newswire.com.