# ESGold Confirms Final Processing Methodology at Montauban as Construction Nears Completion

- Link: https://europeanbusinessmagazine.com/esgold-confirms-final-processing-methodology-at-montauban-as-construction-nears-completion/
- Published: 2025-10-28T12:35:00+00:00
- Author: EBM Mediawire

_**Metallurgical work validates processing approach for railway tailings; construction
progressing ahead of schedule and exploration planning accelerating**_

**VANCOUVER, BRITISH COLUMBIA / [ACCESS Newswire](https://www.accessnewswire.com/)/
October 28, 2025 / ****ESGold Corp. (“ESGold” or the “Company”) (CSE:ESAU)(OTCQB:
ESAUF)(FSE:Z7D)** is pleased to report that recent metallurgical work conducted 
at its fully permitted Montauban Gold-Silver Project in Quebec has validated the
Company’s processing strategy for the railway tailings and other feedstock at the
site.

Gravity separation tests confirmed that concentrate grades from the railbed material
were not sufficient to allow for direct gold and silver pouring. The results confirmed
that while gravity separation did not produce a concentrate sufficient for direct
gold or silver pouring, all Montauban feedstock, including the railway tailings,
will be processed directly through the Merrill Crowe closed circuit as part of the
final phase of mill construction. This outcome provides valuable validation of the
process and confirms the Company’s path forward before finalizing equipment procurement.

### Join The European Business Briefing

New subscribers this quarter are entered into a draw to win a Rolex Submariner. 
Join 40,000+ founders, investors and executives who read EBM every day.

 [Subscribe](https://europeanbusinessmagazine.beehiiv.com/subscribe)

All metallurgical work was supervised by Edmond St-Jean, P.Eng., with testing completed
at the Montauban facility and laboratory analyses performed by ALS Global in Val-
d’Or, Quebec.

**Key Highlights**

 * **Processing Strategy Confirmed:** Metallurgical results validated the Merrill
   Crowe closed circuit as the optimal processing path for all Montauban feedstock,
   ensuring operational efficiency across tailings and railbed material.
 * **De-Risked Equipment Procurement:** The results provide critical technical confirmation
   ahead of finalizing purchase and installation of processing components.
 * **Construction Advancing Ahead of Schedule:** The main mill building is nearing
   completion, with concrete curing and interior finishing underway.
 * **Infrastructure Expansion:** The gold room and on-site laboratory are being 
   constructed to support production assays and future exploration analysis.
 * **Exploration Momentum:** Advanced 3D geological modeling is in its final stages
   and will guide an expanded exploration program designed to test deeper and newly
   defined mineralized structures.

**Gordon Robb, CEO of ESGold, commented:**

“This work gave us exactly what we needed – confirmation of the correct processing
path before finalizing our equipment procurement. The metallurgical data supports
our plan to process all Montauban feedstock through the Merrill Crowe circuit to
be built during the final phase of construction, giving us the confidence to move
ahead decisively. The site looks excellent, and construction is progressing faster
than anticipated. Our gold and lab rooms are coming together beautifully, and we’re
preparing to transition into the installation phase. I want to thank our team for
their dedication and precision in getting us to this point. With construction nearing
completion and exploration planning accelerating, ESGold is entering a very exciting
phase as we move closer to first production.”

**Construction and Exploration Progress**

Construction at Montauban continues to advance rapidly. The main mill structure 
is now complete, with concrete foundations in their final curing phase. Interior
finishing work is ongoing, including the development of a dedicated gold room and
fully equipped on-site laboratory. Once complete, ESGold will begin installing the
processing equipment already on site, including Humphrey spirals and shaker tables,
followed by the remaining Merrill Crowe circuit components to be procured and delivered.

In parallel, ESGold’s geological team in conjunction with _Caur Technologies_ continues
to finalize advanced 3D modeling that integrates geophysical and historical data
to define new exploration corridors and deeper mineralized structures. These findings
will form the foundation of the next exploration phase, designed to expand Montauban’s
resource potential and enhance long-term value creation.

[[

_Construction of the Montauban mill and gold room nearing completion, ESGold Corp.,
September 2025_

**Upcoming Milestones**

 * Completion of mill building and commissioning of on-site gold room and laboratory.
 * Finalization and release of 3D geological model
 * Installation of Merrill Crowe circuit and processing equipment.
 * Launch of expanded exploration targeting program and drill permit applications.
 * Ongoing preparation for 2026 production start.

**Why This Matters to Investors**

The confirmation of ESGold’s processing strategy de-risks the path to production
by validating the use of a single, efficient Merrill Crowe circuit for all Montauban
feedstock. With construction advancing ahead of schedule and exploration planning
in motion, the Company continues to strengthen its position as a fully funded, near-
term gold and silver producer with scalability and long-term growth potential.

**Qualified Person**
The technical content of this news release has been reviewed
and approved by John Langton (P.Geo.), a Qualified Person under _National Instrument
43-101 – Standards of Disclosure for Mineral Projects._ The bench testing summarized
in this press release was supervised by Edmond St-Jean, Ing., whose underlying report
notes that samples were collected from the Montauban site and used as received for
metallurgical analysis. Data and results are preliminary but considered reliable
for disclosure purposes.

**About ESGold Corp.**

[**ESGold Corp.**](https://pr.report/fidn)** (CSE:ESAU)(OTCQB:ESAUF)(FSE:Z7D)** 
is a fully permitted, fully funded, pre-production mining company advancing a scalable
clean mining model across North and South America. The Company’s flagship Montauban
Gold-Silver Project in Quebec is under construction with production anticipated 
in 2026. ESGold is also advancing a joint venture in Colombia, validating one of
South America’s most prolific gold regions for tailings reprocessing and systematic
exploration. With a dual-track strategy of cash flow today and discovery tomorrow,
ESGold is building a platform for clean, sustainable growth and long-term shareholder
value.

For more information, please contact ESGold Corp. at **+1-888-370-1059** or visit
[ esgold.com](https://pr.report/fido) for additional resources, including a French
version of this press release, past news releases, a 3D model of the Montauban processing
plant, media interviews, and opinion-editorial pieces.

Stay connected by following us on[ X](https://pr.report/fidp) (formerly Twitter),
[ LinkedIn](https://pr.report/fidq), and joining our[ Telegram channel](https://t.me/+SQeyLoDRjIAwMDVh).

For further information or to connect directly, please reach out to Gordon Robb,
CEO of ESGold Corp. at [**gordon@esgold.com**](https://europeanbusinessmagazine.com/esgold-confirms-final-processing-methodology-at-montauban-as-construction-nears-completion/gordon@esgold.com)
or call **250-217-2321.**

**On behalf of the Board of Directors**
**ESGold Corp.****Paul Mastantuono****Chairman&
COO**[info@esgold.com](https://europeanbusinessmagazine.com/esgold-confirms-final-processing-methodology-at-montauban-as-construction-nears-completion/info@esgold.com)
+1-888-370-1059

**Cautionary Note Regarding Forward-Looking Information**
This news release contains“
forward-looking information” within the meaning of applicable Canadian securities
laws, including statements regarding metallurgical recoveries, project economics,
construction timelines, and exploration potential. Forward-looking information is
based on reasonable assumptions believed to be current but involves known and unknown
risks and uncertainties that may cause actual results to differ materially. Historical
data referenced herein is not current, has not been independently verified by ESGold,
and should not be relied upon for investment decisions. ESGold disclaims any obligation
to update or revise forward-looking information except as required by law.

_Neither the Canadian Securities Exchange nor its Regulation Services Provider accepts
responsibility for the adequacy or accuracy of this release._

**SOURCE: **ESGold Corp